IFB 1-14-C024: Internet Service Provider, National Airport

PROJECT OVERVIEW
|
IFB Issue Date: February 5, 2014
Deadline for Bids: 2:00 PM (Eastern), March 6, 2014
Pre-Bid Conference: None 
Question Submission: The deadline for submitting questions has passed.
No further questions will be accepted.
Estimated Dollar Value: Up to $60,000 annually
Project Duration: Three-year base period with two three-year options
Bond Requirements: None
Project Summary:
The Contractor shall furnish all necessary labor, materials, tools, equipment and supervision to provide internet access for the Metropolitan Washington Airports Authority offices and personnel located at Ronald Reagan Washington National Airport.
LDBE Requirement:
None
Amendments Issued:
One, February 20, 2014.  The due date for bids is extended from February 26, 2014 to March 6, 2014.
CLICK HERE to download Amendment Documents
Last Updated February 20, 2014