RFP 1-13-C025: Underground Ductbank Rehabilitation and Electrical Feeder Replacement, Dulles Airport

PROJECT OVERVIEW
|
RFP Issue Date: November 19, 2012
Deadline for Proposals: 2:00 PM (Eastern), December 18, 2012
Pre-Proposal Conference: 10:00 AM (Eastern), November 29, 2012 at 4th Floor Conference Room #1, 45025 Aviation Drive, Dulles Airport
Question Submission: The deadline for submitting questions has passed.
No further questions will be accepted.
Estimated Dollar Value: $1,000,000 - $2,500,000
Project Duration: 175 days from Notice to Proceed
Bond Requirements: 100% Payment, 100% Performance
Project Summary:
The Contractor shall furnish all necessary labor, materials, tools, equipment, and supervision to replace two underground ductbank sections, replace cable stanchions, deadbreak junction bars, grounding and general cleanup of Manholes, supply and install two 15Kvolt electrical feeder circuits and remove two existing 15Kvolt electrical feeder circuits at Washington Dulles International Airport.
LDBE Requirement:
This RFP has a 75% Local Disadvantaged Business Enterprise (LDBE) participation requirement and a 25% Voluntary MBE/WBE goal. Firms located within a 100-mile radius and whose 3 year average gross receipts, including all affiliates, do not exceed the size standard(s) below are eligible for consideration. For more LDBE/MBE/WBE information, including other LDBE size standards, contact the Equal Opportunity Programs Department at 703-417-8625.
LDBE Size Standards:
NAICS Code Type of Work / Service LDBE Size Standard
238210 Electrical Contractors and other Wiring Installation Contractors $14.0 Million
238910 Site Preparation Contractors $14.0 Million
Amendments Issued:
One, December 7, 2012.  The due date for proposals remains unchanged.
CLICK HERE to download Amendment Documents
Last Updated December 7, 2012