RFP 1-12-C236: Painting of Airport Structures, National Airport

PROJECT OVERVIEW
|
RFP Issue Date: October 24, 2012
Deadline for Proposals: 2:00 PM (Eastern), November 28, 2012
Pre-Proposal Conference: 10:00 AM (Eastern), November 13, 2012 at the East Building Second Floor Conference Room, National Airport
Question Submission: The deadline for submitting questions has passed.
No further questions will be accepted.
Estimated Dollar Value: $400,000 - $600,000
Project Duration: 270 days from Notice to Proceed
Bond Requirements: 100% Payment, 100% Performance
Project Summary:
The Contractor shall provide all necessary labor, material, equipment, tools and supervision for the painting of various structures at Ronald Reagan Washington National Airport, to include the exterior walls, doors and window frames of Hangars 2 through 7, the exterior surfaces of Passenger Loading Bridges 1 through 9 at Terminal A, the walls of the service corridors, Loading Docks B & C and Operations Level hallways at the North, Center and South Piers and exterior stairways of Terminal B/C.
LDBE Requirement:
This RFP has a 100% Local Disadvantaged Business Enterprise (LDBE) participation requirement and a 50% Voluntary MBE/WBE goal. Firms located within a 100-mile radius and whose 3 year average gross receipts, including all affiliates, do not exceed the size standard(s) below are eligible for consideration. For more LDBE/MBE/WBE information, including other LDBE size standards, contact the Equal Opportunity Programs Department at 703-417-8625.
LDBE Size Standards:
NAICS Code Type of Work / Service LDBE Size Standard
238320 Painting Contractors $14.0 Million
Amendments Issued:
None